Partner Article
Saint-Gobain site successfully energised by high-voltage specialist Smith Brothers
Power engineering contractor Smith Brothers has completed a large-scale assignment to connect the Saint-Gobain Glass manufacturing facility in Eggborough, Goole, to the grid. Saint-Gobain – Europe’s leading flat glass producer – appointed the Independent Connection Provider (ICP) to upgrade the HV system and handle all electrical and civil engineering works to link the facility into the local distribution network.
Following an eight-month turnkey scheme of works – from initial design through to final commissioning – the Smith Brothers team was tasked with replacing the previous private-wire system and conducting essential network reinforcements.
This entailed the construction of two 66kV outdoor substations – one private and one contestable – along with the required cabling works and installation of two parallel-fed 20MVA transformers along the route between the compounds. The engineers additionally established an 11kV substation and control room, and installed all associated electrical and protective equipment.
Having completed the site commissioning in August, the high-voltage specialist has now finished the integration of the system into the NPg and Saint-Gobain networks and successfully energised the site.
Smith Brothers’ senior project manager, John Benson, commented: “Grid connection assignments always require a robust and proactive project management schedule, to ensure all works stay on track and any issues can be resolved as quickly as possible. For manufacturing sites like the Saint-Gobain facility – where smooth operations are key to business success – this is really important, as any unforeseen interruptions can be highly disruptive.
“Thanks to the great organisation and communication of the entire team assigned to the project – as well as the client, NPg and third-party suppliers – we were able to conduct the engineering works efficiently and successfully energise the site.”
Now that the network replacement and reinforcement assignment has concluded, Smith Brothers will be responsible for conducting any required high-voltage upgrades at the site – part of the firm’s wider framework maintenance contract with Saint-Gobain.
Headquartered in Elland, West Yorkshire, Smith Brothers is a leading high-voltage power contractor. With an expanding portfolio of completed network connection assignments throughout the UK – spanning industrial, commercial, renewable and utility sectors – the firm is one of the country’s fastest-growing ICPs.
This was posted in Bdaily's Members' News section by Katie Mallinson .
Enjoy the read? Get Bdaily delivered.
Sign up to receive our popular Yorkshire & The Humber morning email for free.
Why local government is key to devolution success
Your reputation is worth more than that invoice
There is no perfect time when selling a business
What next when social media career help goes?
The psychological contract that nobody signs
Time for strategy built on the foundational economy
Why being ‘work-ready’ matters more than ever
The North's future doesn't end at Manchester
Exit or legacy? Why every owner needs a plan
Who speaks up for SMEs when giants get bigger?
The true value of HR in an AI-driven working world
What new business rates guidance means for pubs